Soviero Bros. Contracting Corp. v. City of New York

Supreme Court of New York, Appellate Division

June 28, 1955

Soviero Bros. Contracting Corp.
v.
City of New York

Page 436

[Copyrighted Material Omitted]

Page 437

[142 N.Y.S.2d 509] Anthony Curreri, New York City, of counsel (Seymour B. Quel, New York City, on the brief; Peter Campbell Brown, Corp. Counsel, New York City), for appellant.

Nelson Rosenbaum, New York City, for respondent.

Before CALLAHAN, J. P., and BREITEL, BASTOW, BOTEIN, and RABIN, JJ.

BREITEL, Justice.

Plaintiff is a contractor who undertook in written agreements with the City of New York to construct two sewers at separate locations and to make the necessary excavations. It sues for damages based on misrepresentations in the City's specifications as to the site of one of the sewer excavations and the physical condition of the sub-surface area of the other. The City sets up as an affirmative defense the time limitation contained in the contracts for the bringing of suits. That provision requires [142 N.Y.S.2d 510] that actions be commenced within one year after the filing in the office of the Comptroller of the final certificate. Concededly, the one-year period has long expired. It is also conceded that the true physical facts were discovered by the contractor more than a year (indeed, more than three years) prior to the beginning of this action.

The issue is whether the City may interpose and rest upon the time limitation as a defense in an action charging it with 'fraudulent' misrepresentation as to material facts, in reliance upon which the contractor entered into its engagements, and which engagements the contractor has never elected to rescind.

The question arises on a motion for summary judgment made by the defendant under Rule 113 of the Rules of Civil Practice. The City Court Special Term granted the motion, but the order was reversed by a divided court in the Appellate Term.

The complaint is framed in law and demands damages in almost the classical form for actual fraud. The affidavits submitted on the motion, on the other hand, reveal that reliance is not had upon the traditional five elements of fraud. On the contrary, the gravamen is misrepresentation, innocently or recklessly made by the City, with respect to material facts, at a time when, somewhere in the files of the City, there were documents and maps clearly revealing the true facts, which facts were never disclosed in advance to the contractor. Since, however, the action is based on damages at law for fraudulent inducement, it is in affirmance of the contracts. This being so, the City may avail itself of the short period of limitation contained in the written agreements with the contractor. Such a

Page 438

contractual period of limitation is not contrary to public policy. Consequently, the order of the Appellate Term should be reversed and the order of Special Term granting judgment in favor of the City should be reinstated.

The complaint contains two causes of action: One is for damages of $3,529.44 based upon the additional expense incurred by the contractor in making one excavation at a site other than the one indicated in the specifications; and the other is for damages in the sum of $1,191.20 for additional expense incurred in removing trolley tracks and railroad ties found at the site of the other excavation, and of which the contractor was not advised at the time of the making of the agreement. The contracts, according to the final certificates, yielded a total payment to the contractor from the City of $29,699, exclusive of these claimed extras.

January 26, 1949, and October 11, 1949, were the dates for the opening of bids on the respective projects. For the first project, a final certificate was filed on November 25, 1949, and payment of the amount certified was made by the City to the contractor on December 28, 1949. On the latter date, the contractor filed a claim with the Comptroller for the excess expenses, in the sum of $3,529.44, sustained at the relocated site. Various proceedings were had under this claim, including an examination [142 N.Y.S.2d 511] of the contractor, and, on November 25, 1952, the City rejected the claim. In the second project, similar proceedings in part were had with respect to the contractor's claim, in the sum of $1,191.20, for additional expenses incurred in removing trolley tracks and railroad ties.

This action was thereafter begun on January 23, 1953, more than three years after the issuance of the final certificate for the first contract and the payment made thereunder.

It is not disputed that the first contract and its specifications called for excavation in an existing dirt area to accommodate a 12-inch sewer. To make such an excavation it was necessary for the work to extend for a width of 14 feet. When the contractor was ready to proceed with the work under this contract, the site for the laying of the sewer had to be changed twice because, on each occasion, it was discovered that the proposed excavation would invade the properties of abutting owners. The site finally chosen for the excavation, free from the objections of abutting owners, lay under a contrete walk. This, of course, entailed additional expense for the contractor. At the location specified in the other contract, when the work pentrated to the sub-surface, there were discovered abandoned

Page 439

trolley tracks and railroad ties, which again increased the expense for the contractor. The contractor protested because of the changed requirements and the additional expense, but proceeded with the work. The additional expenses were the basis for the claims filed with the Comptroller in December, 1949 and May, 1950, respectively. At no time, then or since, did the contractor elect, as it might have, to rescind the contracts, ...


Buy This Entire Record For $7.95

Download the entire decision to receive the complete text, official citation,
docket number, dissents and concurrences, and footnotes for this case.

Learn more about what you receive with purchase of this case.