UNITED STATES v. PANAMA TRANSP. CO.

April 3, 1959

UNITED STATES of America, as charterer, insurer and underwriter, and Socony-Vacuum Oil Company, Incorporated, as owner of The SS MOBILGAS, Libelants,
v.
PANAMA TRANSPORT COMPANY, and The M/V ESSO BALBOA, her engines, tackle, apparel, etc., Respondents



The opinion of the court was delivered by: LEVET

This involves a motion for a final decree by the proctors for the libellants, United States of America and Socony-Vacuum Oil Company, Incorporated. In the interlocutory decree herein, M/V Esso Balboa was held to be solely at fault in the collision on which these proceedings were based. (See D.C., 155 F.Supp. 699.) This determination was affirmed in the Second Circuit. (See 253 F.2d 758.)

The parties have subsequently agreed on a settlement of the hull damage, which has been paid, but a difference now exists with respect to liability for claims for loss of use or detention of the SS Mobilgas. Although by the interlocutory decree the question of damages was referred to a commissioner, the question now arising, possibly having distinct legal connotations not theretofore appearing, led the court to assume the direct determination of the present issue. Consequently, the court, after certain stipulations had been made, as hereinafter referred to, held a hearing, took the evidence, including testimony and exhibits submitted, considered the briefs of the parties, and hereby finds as follows:

Findings of Fact

 1. As heretofore found, the M/V Esso Balboa was solely responsible for the collision between the SS Mobilgas and M/V Esso Balboa on September 19, 1944.

 2. On or about April 29, 1942, Socony-Vacuum Oil Company, Incorporated, as owner of the SS Mobilgas, entered into a time charter on said vessel with the United States of America acting by and through the War Shipping Administration.

 3. At a subsequent date and effective on June 29, 1942, an amended time charter was executed. (See Libellants' Exhibits 8 and 9.)

 4. Clause 4, Part II of this charter as amended contained the following provisions:

 'In the event that the Vessel is detained because of the happening of any event caused or contributed to by another vessel, person, corporation, or others, for which detention such third parties are or may be liable (the period of such detention to include the time necessary to proceed to, survey, and effect repairs unaccomplished upon the date of redelivery of the Vessel under this Charter), then for such period of detention the Charterer's obligation to the Owner for hire and for other sums otherwise accruing hereunder shall cease: Provided, however, That the Charterer shall indemnity and save the Owner harmless from any loss whatsoever by reason of the cessation of such obligations, and notwithstanding said cessation shall pay to the Owner a sum not less than the amount which would otherwise be payable to the Owner for such obligations in the same manner and to the same extent as if such cessation had not occurred, but on performance of this indemnity the Charterer shall immediately become subrogated, to the extent of such indemnity, to all rights whatsoever of the Owner to recover for such detention from or against such vessel, person, corporation, or others, and the Charterer shall be entitled to bring and maintain suit or suits thereon in its own name or in the name of the Owner as the Charterer may see fit: Provided, however, That on the written request of the Charterer, the Owner shall in each instance, assert and prosecute such claims in the name of the Owner, but for and on behalf of the Charterer and at the Charterer's expense, such claims to be in a sum not less than the amount of the indemnity paid by the Charterer.'

 5. The parties at the original trial on May 15, 1957, stipulated that the SS Mobilgas was out of service as a result of the subject collision for the purposes of taking on fresh water, survey, tank cleaning, temporary repairs and permanent repairs, during the following periods of time:

 'Mr. Fleischer: It is hereby stipulated and agreed that the Mobilgas was out of service as a result of the subject collision for purposes of taking on fresh water, survey, tank cleaning, temporary repairs and permanent repairs during the following periods of time as outlined in the port logs of the Mobilgas, which logs are in the possession of Socony-Vacuum Oil Company, Incorporated. At Finschhafen, New Guinea: from 9.34 a.m. on September 19, 1944 to 12.30 p.m. on September 25, 1944. Six days, two hours and 56 minutes.

 'At Panama from 8.46 a.m. on October 26, 1944 to 9.45 a.m. on October 27, 1944. One day, 59 minutes.

 'Then the next period relates to surveying the vessel and her repairs, and that was from 11.07 p.m. on November 9, 1944 to 9.00 a.m. January 26, 1945.' (Record, May 15, 1957, pp. 10-11.)

 6. The parties on the same date further stipulated as to the amounts paid by the United States of America to Socony-Vacuum Oil Company, Incorporated as indemnity for the periods during which the SS Mobilgas was out of service, as follows:

 'It is further stipulated and agreed that the Government indemnified Socony-Vacuum Oil Company, Incorporated for these periods during which the Mobilgas was out of service in the sum of $ 130,484.70, less savings of $ 7,120.55, for a net amount of $ 123,364.15 under the provisions of clause 4, part 2, of the time charter of the Mobilgas, now Exhibit U.S. No. 9, for which claim the Government was subrogated ...


Buy This Entire Record For $7.95

Download the entire decision to receive the complete text, official citation,
docket number, dissents and concurrences, and footnotes for this case.

Learn more about what you receive with purchase of this case.