LASKER-GOLDMAN CORPORATION v. DELMA ENGINEERING CORPORATION (04/02/69)

SUPREME COURT OF NEW YORK, APPELLATE DIVISION, FIRST DEPARTMENT


April 2, 1969

LASKER-GOLDMAN CORPORATION, RESPONDENT,
v.
DELMA ENGINEERING CORPORATION, APPELLANT, ET AL., DEFENDANTS

Order entered December 17, 1968, granting plaintiff partial summary judgment against defendant under the first cause of action unanimously reversed, on the law, with $50 costs and disbursements, and the motion for summary judgment denied.

Concur -- Stevens, P. J., Eager, Capozzoli, Markewich and Steuer, JJ.

Plaintiff's claim against defendant under this cause is based upon a straight indemnity clause whereby defendant agreed to hold plaintiff "harmless from all liability, loss, cost or damage" arising out of defendant's performance as plaintiff's subcontractor on a portion of certain construction work. Third parties have made claims for damage arising out of a mishap on the job, but, as far as is disclosed by the record, at the time of institution of the action, matters had not gone further than the filing of claims with plaintiff. This is not an action for declaration of the rights of the parties, but is, in effect, a claim over by plaintiff against defendant. Plaintiff is as yet entitled to nothing from defendant, and the cause is asserted prematurely.

19690402

© 1998 VersusLaw Inc.



Buy This Entire Record For $7.95

Official citation and/or docket number and footnotes (if any) for this case available with purchase.

Learn more about what you receive with purchase of this case.