Spencer, White & Prentis Inc. v. United States Environmental Protection Agency

decided: February 10, 1981.

SPENCER, WHITE & PRENTIS, INC. AND SEATEC INTERNATIONAL, LTD., A JOINT VENTURE, AND MORRISON-KNUDSEN COMPANY, INC., PLAINTIFFS-APPELLANTS,
v.
UNITED STATES OF AMERICA ENVIRONMENTAL PROTECTION AGENCY, SOUTHWEST SEWER DISTRICT IN THE COUNTY OF SUFFOLK, AKA COUNTY SEWER DISTRICT NO. 3, COUNTY OF SUFFOLK OF THE STATE OF NEW YORK, AND GREAT AMERICAN INSURANCE COMPANY, DEFENDANTS-APPELLEES .



Appeal from an order of the District Court for the Eastern District of New York, entered by Judge Henry Bramwell, granting summary judgment dismissing the complaint of plaintiffs, who are disappointed bidders for completion of a federally subsidized sewer system, seeking damages and declaratory relief on the ground that the contract was awarded illegally and claiming that the EPA Regional Administrator was arbitrary and capricious in upholding rejection of their contract bids, which is alleged to be contrary to federal statutes and regulations, 5 U.S.C. §§ 702.06; 40 C.F.R. §§ 35.938, 35.939, 30.1120 (1980). Affirmed .

Before Lumbard, Mansfield and Meskill, Circuit Judges.

Author: Mansfield

Plaintiffs, Spencer, White & Prentis, Inc. (Spencer), a joint venture with its subsidiary Seatec International Ltd., and Morrison-Knudsen Company, Inc., were bidders on a contract for completion of a federally subsidized sewer system being constructed for the County of Suffolk, New York (Suffolk), a state subdivision.*fn1 Plaintiffs claim that their bids were rejected by Suffolk in favor of another joint venture, Edward B. Fitzpatrick, Jr. Construction Corp. and Arundel Corp. (Fitzpatrick-Arundel), as the result of fraud, contractual invalidity and violation of regulations issued under the Federal Water Pollution Control Act, 33 U.S.C. §§ 466, et seq. (Act). After failing to obtain relief from the United States Environmental Protection Agency (EPA), which had granted funds under the Act for the project and therefore exercised some supervisory administration over it, plaintiffs sued that Agency, Suffolk and the Great American Insurance Company (American), surety for Fitzpatrick-Arundel, to whom the contract was let by Suffolk after renegotiation. Plaintiffs sought damages and declaratory relief. Judge Henry Bramwell granted summary judgment in favor of the defendants dismissing the action on the ground that rejection of plaintiffs' bids was, as found by the EPA Regional Administrator, for "good cause" under the Act. We affirm.

In 1977 Fitzpatrick-Arundel was awarded a contract by Suffolk to lay sewer pipe for the county's federally subsidized water pollution control project in Great South Bay, near Islip, New York. As low bidder it agreed to construct the sewer pipe portion of the project for $10,646,000. Defendant Great American Insurance Company was the surety for Fitzpatrick-Arundel's bid. The sewer pipe was part of a water pollution control project to be constructed for Suffolk's Southwest Sewer District No. 3 at an estimated cost of $307,600,000, of which.$230,700,000 would be reimbursed by the EPA to Suffolk under the terms of the Federal Water Pollution Control Act, 33 U.S.C. §§ 466, et seq., and the Clean Water Act, 33 U.S.C. § 1282.

In April, 1979, Suffolk announced that it considered Fitzpatrick-Arundel to be in default for inadequate progress on the job. Negotiations then began with the surety, American, to determine the future course of the project. When these negotiations reached an impasse, Suffolk advertised for bids to complete the unfinished part of the project, without announcing that it was still negotiating with the surety or that its solicitation of bids was only tentative. Spencer was the lowest responsive bidder at $13,850,000, and plaintiff Morrison-Knudsen Company was second lowest at $27,000 more.

Meanwhile Suffolk continued negotiations with the surety. On July 27, 1979, Spencer filed with Suffolk a bid protest, as permitted by 40 C.F.R. § 35.939,*fn2 issued by the EPA under the Act, asserting that it should be awarded the contract. On August 9, Suffolk and the surety signed a new contract, in which Fitzpatrick-Arundel was reinstated to complete the job. Pursuant to 40 C.F.R. § 35.939(h), Spencer asked the EPA to send Suffolk and the surety a letter prohibiting them from executing the new contract until 10 days after delivery of the protested decision to the parties in interest. The EPA did so. The parties disagree over whether Suffolk complied with this requirement, with Spencer claiming that the contract was executed on August 9 and Suffolk claiming that only the surety executed the contract on August 9, while Suffolk waited until September 18 to execute the contract for its part. On August 13, 1979, Suffolk informed plaintiffs that it was rejecting their protest.

Spencer next filed a protest appeal with the Regional Administrator of the EPA which, as the funding agency, performs a general supervisory function over such projects. Spencer claimed that the surety had waived its right to complete the job by failing to reach an agreement with Suffolk prior to the latter's advertisement for new bids, that Suffolk had waived its right to continue negotiations with the surety for completion of the job by failing to require the surety to complete the job before advertising for new bids, that Suffolk had engaged in bid fraud by advertising for new bids without disclosing that it was still negotiating with the surety, and that Suffolk's rejection of the bids was not based on "good cause," as required by § 35.938-4(h)(2), which states "Unless all bids are rejected for good cause, award shall be made to the low, responsive, responsible bidder." Jurisdiction to protest before the Administrator was premised upon this provision and on the bid advertisement's statement, in conformity with 40 C.F.R. § 35.938-4(b)(5), that the procurement would be "subject to regulations contained in 40 C.F.R. 35.936, 35.938, and 35.939."

The Regional Administrator rejected plaintiffs-appellants' claim, finding that Suffolk had acted with good cause in rejecting all bids for the completion contract. He accepted Suffolk's argument that it felt constrained to let the surety continue with the contract because it believed Fitzpatrick-Arundel would sue it for wrongful termination and knew that a victory for Fitzpatrick-Arundel in that suit would cancel the surety's obligation, leaving the county with a bill for significantly more than the $10,646,000 originally budgeted. By agreeing with the surety to let Fitzpatrick-Arundel continue with the job, the Regional Administrator observed, Suffolk was increasing the likelihood that any costs above the originally budgeted amount would be borne by the surety rather than by Suffolk County taxpayers. Having found the County's rejection to be supported by good cause, he declined to rule on whether Spencer's procurement procedures violated federal law. Finally, in exercise of his duty under federal regulations, the Administrator declined to examine issues which rested primarily on state law. Accordingly, he dismissed all claims against Suffolk and the surety.*fn3

Appellants' suit in the federal district court challenged the Regional Administrator's decision, seeking damages and declaratory relief. On May 29, 1980, Judge Bramwell upheld the Regional Administrator in an order granting summary judgment to the defendants. Judge Bramwell rejected defendants' jurisdictional attacks on the appellants' case, but agreed that the bid rejection was supported by good cause and was not arbitrary or capricious.

Discussion

The role of the federal government in overseeing bidding for construction contracts partially funded under the Federal Water Pollution Control Act is narrowly circumscribed. Once the EPA has granted funds to projects like the parent project in the present case for the pipeline job in Great South Bay, it plays only a general supervisory role over the administration of the projects. Federal regulations explicitly relegate most decisionmaking and conflict resolution to the states. The state or municipal agency runs the project, makes budget adjustments, and monitors the submission and awarding of bids. Localities are permitted to use their own procurement systems and procedures as long as they meet the threshold federal standards, 40 C.F.R. § 35.936-2(a). The Regional Administrator relies on a grantee's determination regarding the application of state or local law to issues which are primarily determined by such law, 40 C.F.R. § 35.936-2(b). The locality (such as Suffolk) is given primary responsibility for the administration and completion of the project and is required to resolve all disputes including those involving invitations for bids and selection of contractors, § 35.936-5(a). To underscore the essentially passive, reviewing function of the EPA, see § 35.936-6, the regulations and the advertisement for bids provide that neither the EPA nor the United States is a party to the contract for construction of the project, §§ 35.936-8, 35.938-4.

Here, state law amply proscribes bid fraud and other improper bidding practices, see N.Y.Gen.Mun.L. § 103,*fn4 so that we need not examine the plaintiffs' claims with respect to these alleged violations. Our role is therefore limited to that of determining whether the Regional Administrator acted arbitrarily or capriciously in finding good cause for Suffolk's rejection of all completion bids, 5 U.S.C. §§ 702-06, and leaving the plaintiffs free to pursue their state law claims in the state court. Appellees insist that we should not reach the merits of this issue, because sovereign immunity bars this suit against the EPA, and because disappointed bidders like Spencer and Morrison-Knudsen have no standing to sue in federal court. We reject these contentions as inapplicable when the disappointed bidder sues under the Administrative Procedure Act, 5 U.S.C. §§ 702-06, attacking final agency action under regulations that explicitly provide for private rights of action.

Appellees' argument that this appeal is barred by sovereign immunity rests on our recent decision in Estate of Watson v. Blumenthal, 586 F.2d 925 (2d Cir. 1978). However, that case held only that the 1976 amendments to the Administrative Procedure Act waiving sovereign immunity defenses in actions brought under the Act did not eliminate that defense in actions brought under the federal question statute, 28 U.S.C. § 1331. Those same amendments make sovereign immunity an untenable defense here in an action which is based essentially on an alleged erroneous ruling by a federal agency. See Brown v. Chrysler Corp., 441 U.S. 281, 317, 99 S. Ct. 1705, 1725, 60 L. Ed. 2d 208 (1979); Califano v. Sanders, 430 U.S. 99, 97 S. Ct. 980, 51 L. Ed. 2d 192 (1977).

Appellees' alternative claim that Spencer and Morrison-Knudsen lack standing to appeal is based on the Supreme Court's holding in Perkins v. Lukens Steel Co., 310 U.S. 113, 60 S. Ct. 869, 84 L. Ed. 1108 (1940), to the effect that unsuccessful bidders for government contracts have no standing to challenge federal procurement action pertaining to the award of any contract. The Court stressed in that case that bidding procedures were for the benefit of the public generally, not for the benefit of the bidders. However, Perkins antedated the passage of the Administrative Procedure Act, which expands federal judicial review of final agency actions. In Scanwell Laboratories, Inc. v. Shaffer, 137 U.S. App. D.C. 371, 424 F.2d 859 (D.C.Cir.1970), the District of Columbia Circuit held that Perkins did not survive the Act, which was enacted for the purpose of guaranteeing recourse to the courts for plaintiffs injured by government officials' failure to follow their own regulations. Five other circuits have followed this rule. Merriam v. Kunzig, 476 F.2d 1233 (3d Cir.), cert. denied, 414 U.S. 911, 94 S. Ct. 233, 38 L. Ed. 2d 149 (1973); Wilke, Inc. v. Department of the Army, 485 F.2d 180 (4th Cir. 1973); Hayes International Corp. v. McLucas, 509 F.2d 247 (5th Cir.), cert. denied, 423 U.S. 864, 96 S. Ct. 123, 46 ...


Buy This Entire Record For $7.95

Download the entire decision to receive the complete text, official citation,
docket number, dissents and concurrences, and footnotes for this case.

Learn more about what you receive with purchase of this case.