SADOWSKY v. CITY OF NEW YORK

January 12, 1984

HAROLD SADOWSKY, VINCENT RUISI and CHELSEA WEST ASSOCIATES, Plaintiffs, against CITY OF NEW YORK and ANTHONY GLIEDMAN, as Commissioner of the Department of Housing Preservation and Development of the City of New York, Defendants.


The opinion of the court was delivered by: CARTER

CARTER, District Judge

Plaintiffs, Harold Sadowsky, Vincent Ruisi, and Chelsea West Associates *fn1" seek a preliminary injunction pursuant to Rule 65(a), F.R.Civ.P., to enjoin the application of Local Law 19, a recently enacted section of the New York City Administrative Code. The law's purpose is to prevent the harassment and displacement of residents in "single room occupancy" dwellings, ("SROs"), who are generally poor and elderly, and otherwise vulnerable to the tactics used by landlords in attempts to evict them without proper judicial proceedings. The law restricts the conversion of SROs to other uses where harassment of residents has been used to vacate such buildings and facilitate their conversion to more financially profitable property.

 Pursuant to Local Law 19, plaintiffs were denied a building permit, which was necessary to enable them to renovate two vacant, dilapidated and concededly uninhabitable buildings that they had contracted to purchase approximately two months before the enactment of Local Law 19. Plaintiffs allege that the law is unconstitutional as applied to them because the law effects a "taking" without just compensation in violation of the Fifth and Fourteenth amendments. They have requested injunctive relief, in addition to damages. Because, as explained below, plaintiffs cannot satisfy this Circuit's standard for preliminary injunctive relief, their request is denied.

 Background

 1. Local Law 19

 Local Law 19 requires owners of RSOs to obtain a certification of no harassment before they may alter or demolish their property since no building premits may be granted without certification. The law generally restricts any party from altering an SRO building for approximately 36 months if harassment is found to have occurred on the premises during the relevant statutory period. *fn2" Although, in this way, the law may prevent owners from developing vacant buildings when they themselves have not committed or participated in acts of harassment if a certification of no harassment cannot be obtained with regard to the premises, the absence of such a restriction would allow landlords, after harassing tenants to vacate the premises, to realize a profit by selling the vacant (buildings) to developers at prices reflecting the buildings' potential value after their conversion, and thus, to escape the law's sanctions.

 There are, nevertheless, some cases in which the law authorizes waivers of the certification requirement. *fn3" Individuals who obtained their interest in an SRO building before May 5, 1983, the date corresponding to probable public notice of the law's regulatory scheme, *fn4" are not required to obtain no harassment certification. *fn5" To secure the waiver, the law requires that such individuals have recorded a deed or contract for the purchase of an SRO building prior to May 5, 1983. Recordation is mandated to insure against collusion between unqualified SRO owners and prior owners, such as the backdating of documentation surrounding the contract. *fn6"

 2. Plaintiff's Transaction

 According to plaintiffs, Sadowsky and Ruisi *fn7" entered into a contract to purchase the premises at 332-334 West 19th Street on March 18, 1983. The buildings on the property had been SRO multiple dwellings that had been vacant for approximately six months before plaintiffs contracted to buy them. The partnership planned to completely renovate the two buildings by expanding and converting them into ten residential apartments. *fn8"

 Plaintiffs submitted an application for a building permit to the Building Department on May 10, 1983. Because the previous owners also had an application on file, the Building Department declined to consider either application until one was withdrawn, which apparently did not occur until some time after June 24, 1983, the closing date. On July 1, 1983, the forms relating to applications for certificates of no harassment were made available pursuant to Local Law 19, and on July 8, plaintiffs submitted their application. In connection with the application, plaintiffs also sought a waiver of certification of no harassment which they premised on a pre-May 5th contract of sale date with respect to the property at issue.

 Plaintiffs had not recorded their contract, but in their application they submitted other evidence concerning the contract date. On October 7, 1983, three months after the application had been filed, it was denied. The Department of Housing Preservation and Development found that plaintiffs did not qualify for a waiver of certification of no harassment since the contract of sale had not been recorded prior to May 5th. The Department also informed plaintiffs that there was reasonable cause to believe that harassment had occurred at 332-334 West 19th Street during the inquiry period, May 10, 1980 -- May 10, 1983, and that a hearing would be held to determine whether the allegations of harassment were accurate.

 Plaintiff's claim for preliminary relief centers upon the economic injury they have sustained and will continue to suffer as a result of the law's "Draconian" effects.Sadowsky Affidavit at 8. The plaintiffs maintain that if they must forego the planned development of the buildings at issue here until three years from the last date harassment is found to have occurred, as the law prescribes, the economic viability of the property will be destroyed. The law produces an unconstitutional taking, plaintiffs contend, because it prohibits use of the property for any reasonable beneficial purpose. In addition, application of the law as to plaintiffs will result in irreparable injury, they allege, because plaintiffs are facing bankruptcy in consequence of the expenses the partnership has incurred thus far, and will be unable to carry the project during the required waiting period.In seeking preliminary injunctive relief, plaintiffs seek the right to begin redevelopment of the subject buildings pending the Court's final decision on the merits.

 Determination

 Preliminary relief is an extraordinary remedy which should not be granted routinely. Medical Society of the State of New York v. Toia, 560 F.2d 535, 538 (2d Cir. 1977). The standard established in this Circuit requires two distinct inquiries. See Arrow United Industries v. Hugh Richards, Inc., 678 F.2d 410 (2d Cir. 1982). Plaintiff must demonstrate (a) irreparable harm and (b) either (1) a likelihood of success on the merits or (2) sufficiently serious questions going to the merits to make them a fair ground for litigation and a balance of hardships tipping decidedly in plaintiffs' favor. Jackson Dairy, Inc. v. H.P. Hood & Sons, Inc., 596 F.2d 70, 72 (2d Cir. 1979). In this case, however, the question of injury and hardship must be set aside *fn9" ...


Buy This Entire Record For $7.95

Download the entire decision to receive the complete text, official citation,
docket number, dissents and concurrences, and footnotes for this case.

Learn more about what you receive with purchase of this case.