Corchado v. City of New York

NEW YORK SUPREME COURT, APPELLATE DIVISION, FIRST DEPARTMENT


July 2, 2009

ANNA CORCHADO, PLAINTIFF-RESPONDENT,
v.
THE CITY OF NEW YORK, DEFENDANT,
CONSOLIDATED EDISON COMPANY OF NEW YORK, INC., DEFENDANT/THIRD PARTY PLAINTIFF-RESPONDENT,
THE HALLEN CONSTRUCTION CO., INC., THIRD-PARTY DEFENDANT-APPELLANT.

Order, Supreme Court, New York County (Paul G. Feinman, J.), entered March 18, 2008, which, in an action for personal injuries sustained in a trip and fall over a pothole allegedly created by the negligence of defendants City or Consolidated Edison, and a third-party action by Consolidated Edison against its contractor (Hallen), insofar as appealed from, denied, as untimely, Hallen's motion for summary judgment dismissing the complaint and third-party complaint, unanimously affirmed, without costs.

Published by New York State Law Reporting Bureau pursuant to Judiciary Law § 431.

This opinion is uncorrected and subject to revision before publication in the Official Reports.

Andrias, J.P., Sweeny, McGuire, Acosta, Renwick, JJ.

117716/05 & 590548/06

The parties' so-ordered stipulation clearly provided that summary judgment motions were "to be filed" within 60 days of the filing of the note of issue. Since the note of issue was filed on October 24, 2007, summary judgment motions were to be filed by December 23, 2007. While Hallen served its motion on December 21, 2007, it did not file the motion until January 4, 2008. Plaintiff's opposition asserted the untimeliness of Hallen's motion, to which Hallen replied that its motion was timely because served within 90 days of the filing of the note of issue. We reject Hallen's argument that CPLR 3212(a) authorizes a court to set a deadline only for the making, i.e., service, not the filing, of summary judgment motions (see e.g. Corbi v Avenue Woodward Corp., 260 AD2d 255, 255 [1999]) because the parties, with the court's consent, were free to chart a procedural course that deviated from the path established by the CPLR (see Katz v Robinson Silverman Pearce Aronsohn & Berman LLP, 277 AD2d 70, 73 [2000] ["Parties are afforded great latitude in charting their procedural course through the courts, by stipulation or otherwise"] [internal citations omitted]). Thus, we affirm the denial of Hallen's motion as untimely since Hallen offered no excuse for the late filing (see Brill v City of New York, 2 NY3d 648, 652 [2004]), and we decline to consider Hallen's contention that good cause exists to consider the motion because the parties misread the so-ordered stipulation and believed that the 60-day deadline applied to the serving, not the filing, of summary judgment motions. That contention was raised improperly for the first time on appeal. In view of the foregoing, we decline to reach the merits of Hallen's motion.

THIS CONSTITUTES THE DECISION AND ORDER OF THE SUPREME COURT, APPELLATE DIVISION, FIRST DEPARTMENT.

20090702

© 1992-2009 VersusLaw Inc.



Buy This Entire Record For $7.95

Official citation and/or docket number and footnotes (if any) for this case available with purchase.

Learn more about what you receive with purchase of this case.