Searching over 5,500,000 cases.


searching
Buy This Entire Record For $7.95

Download the entire decision to receive the complete text, official citation,
docket number, dissents and concurrences, and footnotes for this case.

Learn more about what you receive with purchase of this case.

Tadco Construction Corp. v. Dormitory Authority of the State of New York

March 19, 2010

TADCO CONSTRUCTION CORP. AND THOMAS DEMARTINO, PLAINTIFFS,
v.
DORMITORY AUTHORITY OF THE STATE OF NEW YORK, TYRONE MIDDLETON, PAT CINELLI, JAMES GRAY, JACK KEMP AND JOHN DOES #1-#5, DEFENDANTS.



The opinion of the court was delivered by: David G. Trager United States District Judge

Trager, J

MEMORANDUM AND ORDER

This case arises out of a troubled construction contract between TADCO Construction Corporation ("TADCO") and the Dormitory Authority of the State of New York ("DASNY") to build a new dormitory facility on Staten Island. Plaintiff TADCO alleges multiple breach of contract claims against DASNY, and further alleges a due process violation under 42 U.S.C. § 1983 stemming from purportedly defamatory comments made by DASNY during its termination of the contract with TADCO and from DASNY's failure to pay TADCO promptly for work performed. Plaintiff Thomas DeMartino ("DeMartino"), TADCO's on-site superintendent and management representative, additionally asserts federal and state claims of false arrest, malicious prosecution and abuse of process, claiming that DASNY employees Tyrone Middleton, Pat Cinelli, Jack Kemp and John Doe improperly had him arrested for trespassing at the job site on two separate occasions. Defendants have moved to dismiss all of plaintiffs' federal claims as well as DeMartino's state law claims, and have requested that this court decline to exercise supplemental jurisdiction over TADCO's state law claims. For the reasons explained below, this motion is granted in part and denied in part.

Background

(1) Contractual Disputes between TADCO and DASNY

a. Project Delays

The following facts are drawn from plaintiff's pleadings and, for purposes of this motion, are presumed to be true. In May 2005, defendant DASNY began soliciting bids for a new tenbed residence building for the Staten Island Developmental Disabilities Services Office (the "project"). Compl. ¶ 14. The project was structured as a "multi-prime" project, meaning that four prime contractors would perform discrete segments of the project under the direct supervision of DASNY. Id. at ¶¶ 15-16. Four separate prime contracts were therefore awarded: one for general construction work, one for mechanical work, one for electrical work and one for plumbing work. Id.

Plaintiff TADCO, a general construction contractor, bid on and was awarded the contract for general construction work (the "contract") around June 15, 2005. Id. at ¶¶ 17, 23. Prior to the instant dispute, TADCO had often been awarded state and municipal public works contracts and had previously worked with DASNY several times. Id. at ¶ 13. The contract specified that the project was to be completed by September 29, 2006. See Compl., Ex. A at 2 (contract between TADCO and DASNY).

However, the project was plagued with delays and problems from the outset. Plaintiffs generally attribute these delays to DASNY's funding problems and DASNY's poor management of the other prime contractors. Id. at ¶¶ 19-24. More specifically, TADCO points to several delays that were caused by events outside of its control and within DASNY's control. First, plaintiffs allege that their commencement of the project was delayed by approximately five months when DASNY unexpectedly required TADCO to perform some up-front work not included in the plans and specifications, including building a construction fence around the jobsite, id. at ¶¶ 25-29, and probing and underground radar work to locate existing utility lines, id. at ¶¶ 30-34. As a result of requiring this extra work, DASNY agreed to extend the completion date of the project by six weeks, from September 29, 2006, to November 15, 2006. Id. at ¶ 35. Then, a major design defect in the framing of the building set back TADCO's progress on the project further throughout June and July 2006. Id. at ¶ 41.

Further delays ensued as a result of the slow progress of the mechanical, electrical and plumbing work contractors (collectively, the "MEP contractors"). Id. at ¶¶ 42-50. TADCO believed the MEP contractors' deficient performance was the fault of poor supervision and direction on the part of DASNY, and approached DASNY with concerns over the progression of the project several times. Id. at ¶ 51. In a September 13, 2006 meeting, TADCO explains that DASNY "acknowledged its responsibility to provide overall project management and coordination," promised to provide better supervision and coordination of the four prime contractors in the future and again extended the project completion date, this time until December 7, 2006. Id. at ¶ 52. Nevertheless, problems with the MEP contractors' performance continued throughout the fall of 2006. These problems led DASNY, in early December 2006, to extend the project completion date to January 11, 2007. Id. at ¶ 61.

At the same time these MEP delays were occurring, a dispute erupted between DASNY and TADCO regarding a contract provision that required TADCO to backfill open trenches at the jobsite with soil taken from on-site. Id. at ¶ 62. At some point, apparently during the summer of 2006 (the complaint specifies only "prior to September 2006"), TADCO discovered that the soil at the site was not suitable for use as backfill because of its high moisture content. Id. at ¶ 63. TADCO attributed its late discovery of this moisture problem to DASNY's failure to provide TADCO with any soil boring logs or geotechnical data. Id. at ¶ 64. Therefore, it asked DASNY to resolve the problem during fall of 2006. However, according to TADCO, DASNY was simply non-responsive. Id. at ¶¶ 66-73.

b. Thomas DeMartino's Arrests

In November, this unresolved backfill problem provoked a disagreement between an employee of DASNY and an employee of TADCO. One of DASNY's field representatives and now a named defendant, Tyrone Middleton, ordered DeMartino, TADCO's onsite project superintendent, to cover the open trenches at the jobsite with wood planks on November 9, 2006. Id. at ¶¶ 75-76. DeMartino refused, explaining that this work was not specified in the contract and would require extra labor, materials, supplies and equipment. Id. at ¶¶ 77-78. Middleton responded this same day by lodging a criminal complaint against DeMartino with the state police officers assigned to the facility, claiming that DeMartino was trespassing. Id. at ¶¶ 80, 134. The complaint additionally alleges that Pat Cinelli, the Director of DASNY's Statewide Utilities Unit, and/or Jack Kemp, the Chief of Construction Contracts for DASNY, "approved of and authorized" Middleton's actions in having DeMartino arrested. Id. at ¶ 139. As a result of Middleton's complaint, DeMartino was arrested, taken to the local precinct and issued a criminal summons for trespassing. Id. at ¶ 82.

Apparently, however, this arrest did not dissuade DeMartino from returning to the job site. In early January 2007, Middleton or some other DASNY personnel lodged a second criminal complaint against DeMartino, who was once again arrested for trespassing at the job site. Id. at ¶¶ 84-86. DeMartino spent one night in jail and was subsequently charged with criminal trespassing. Both of the trespassing charges were subsequently dismissed in their entirety. Id. at ¶¶ 83, 87.

c. Disputed Work

Throughout the course of TADCO's performance under the contract, DASNY repeatedly directed TADCO to perform "charge order" work, i.e., work not included within the contract fee negotiated. Id. at ¶¶ 88-89. DASNY at times used the "disputed work clause" in the contract to force TADCO to perform this work by claiming the work was "disputed." Id. TADCO believed the contract entitled it to payment for the value of this extra work and requested payment, but DASNY allegedly delayed the processing of the charge orders for this work due to a lack of funding. Id. at ¶¶ 89-90. The accrual of several hundred thousand dollars of unpaid charge order work by December 2006 led TADCO to file an action in state court against DASNY on January 5, 2007, in which it sought to recover damages for "abuse of State process, failure to provide proof of funding, breach of implied covenants of good faith and fair dealing, and breach of contract." Id. at ¶¶ 93-94. Neither party has provided any further information on the status of this state court action.

d. Termination of the Contract

At the time TADCO filed the state court lawsuit against DASNY, it estimates that it had completed over eighty-five percent of its work on the project. Id. at ¶ 95. However, TADCO asserts that, although it was willing and able to complete the project, it could not move forward without DASNY resolving the soil problem and problems with the MEP contractors, or responding to several requests for information that TADCO had submitted to DASNY. Id. at ¶¶ 96-99. TADCO's president reiterated this position in a letter to Jack Kemp, DASNY's Chief of Construction, on January 2, 2007. Id. at ¶ 99.

DASNY, however, believed that TADCO had failed to perform its obligations under the contract and did not demonstrate the ability to complete the work. Id. at ¶ 103. Although the parties exchanged several letters apparently attempting to come to some agreement, DASNY ultimately chose to terminate the contract with TADCO on January 17, 2007. Id. at ¶¶ 100-07. TADCO believes this termination was wrongful. As evidence, it points to the results of an investigation by First Sealord Surety, Inc., the bonding company that issued the performance and payment bonds on the project. Id. at ¶ 108. First Sealord Company's independent investigation report of March 28, 2007 concluded that "DASNY's election to terminate TADCO was unjustified and improper." Id. At the time of termination, DASNY reportedly owed TADCO $79,485.00 for completed contract work and $45,402.31 in retainage, in addition to the money it owed for TADCO's extra work, none of which has been paid to TADCO. Id. at ¶ 110-11.

Around the same time the contract was terminated, TADCO asserts that James Gray, DASNY's Managing Director of Construction, Jack Kemp and/or other persons associated with DASNY made false and "defamatory allegations concerning TADCO's purported failure to perform its obligations under the Contract and to complete the Project," to the MEP contractors, TADCO's subcontractors and others within the construction industry. Compl. ¶ 109.

(2) The Current Action

On the basis of the above facts, TADCO and DeMartino brought the current action in federal court on January 7, 2008. The complaint alleges thirty-nine causes of action, which can generally be grouped as: (1) violations of the Due Process clause under the Fifth and Fourteenth Amendments and 42 U.S.C. § 1983 against DASNY, Gray, Kemp and John Does (1st Cause of Action); (2) malicious prosecution, abuse of criminal process and false arrest under the Fourth, Fifth and Fourteenth Amendments and 42 U.S.C. § 1983 against DASNY, Middleton, Cinelli, Kemp and John Doe (2nd--7th Causes of Action); (3) malicious prosecution, abuse of criminal process and false arrest under New York law (34th--39th Causes of Action); (4) wrongful termination of the contract against DASNY (8th Cause of Action); (5) twenty-one breach of contract claims against DASNY (9th--30th Causes of Action); (6) quantum meruit against DASNY (31st-32nd Causes of Action); and (7) unjust enrichment against DASNY (33rd Cause of Action).

Defendants have moved under Fed. Rule Civ. Proc. 12(b)(6) to dismiss TADCO's § 1983 due process claim and DeMartino's federal and state false arrest, malicious prosecution and abuse of process claims (1st--7th and 34--39th Causes of Action). They first argue that TADCO has not stated a claim that rises to the level of a due process violation and instead is impermissibly attempting to constitutionalize a state law contract claim. With respect to DeMartino's claims, defendants primarily argue that DASNY had exercised its contractual right to bar DeMartino from the job site and, therefore, DeMartino was in fact trespassing on both the occasions he was arrested. Accordingly, defendants request that all of plaintiffs' federal claims be dismissed. Although defendants are not at this time challenging the adequacy of TADCO's state law claims (8th--33rd Causes of Action), they suggest that the court should decline to exercise supplemental jurisdiction over these claims.

TADCO, who is still represented by counsel, has submitted a Memorandum of Law in Opposition to Defendant's Motion to Dismiss (hereinafter "Pl.'s Mem."). However, DeMartino, who is now proceeding pro se after TADCO's counsel withdrew from his representation in October 2008, has submitted no opposition. See Pl.'s Mem. at 18 n.1. The implications of DeMartino's failure to respond are discussed infra.

Discussion

(1) Treatment as a Motion to Dismiss and Standards Governing Motions to Dismiss

Preliminarily, it must be determined whether to treat the instant motion as a motion to dismiss or to convert it into one for summary judgment, given that both parties have submitted some materials outside the pleadings. "When matters outside the pleadings are presented in response to a 12(b)(6) motion, a district court must either exclude the additional material and decide the motion on the complaint alone or convert the motion to one for summary judgment under Fed. R. Civ. P. 56 and afford all parties the opportunity to present supporting materials." Friedl v. City of New York, 210 F.3d 79, 83 (2d Cir. 2000) (internal marks omitted). "A district court, however, is not obliged to convert a 12(b)(6) motion to one for summary judgment in every case in which a defendant seeks to rely on matters outside the complaint in support of a 12(b)(6) motion; it may, at its discretion, exclude the extraneous material and construe the motion as one under Rule 12(b)(6)." Toussie v. Town Bd. of East Hampton, 08-CV-1922, 2010 WL 597469, at *3 n.1 (E.D.N.Y. Feb. 17, 2010) (internal quotation marks omitted).

At this stage, defendants' 12(b)(6) motion will not be converted into a motion for summary judgment, as defendants have not urged the court to consider its motion as one for summary judgment in the alternative, defendants have not filed an answer and it appears from the documents presented that key facts are yet to be discovered. See id. (declining to convert 12(b)(6) motion into motion for summary judgment where no answer had been filed and discovery was not yet complete); cf. Pani v. Empire Blue Cross Blue Shield, 152 F.3d 67, 75-76 (2d Cir. 1998) (finding that 12(b)(6) motion could have been converted into one for summary judgment where "[t]he government moved for summary judgment in the alternative" and thereby gave the opposing party "sufficient notice" and "ample opportunity to submit supporting affidavits and evidence").

Nevertheless, one document outside of the pleadings will be considered in ruling on this motion. Although plaintiffs' complaint attached only a short governing contract, the contract signed between DASNY and TADCO incorporates by reference a longer document containing the contract's General Conditions and Specifications and Drawings, which defendants have appended to their motion. See Decl. of Joel Graber ("Graber Decl."), Ex. B. The General Conditions, although not part of plaintiffs' pleadings, are integral to plaintiffs' complaint, as plaintiffs rely on them to state, inter alia, claims that the contract was improperly terminated, that TADCO had a right to payment for the value of extra work it performed and that defendants had no contractual right to exclude DeMartino from the job site. See Meyer Pincus & Assocs., P.C. v. Oppenheimer & Co., 936 F.2d 759, 762 (2d Cir. 1991) (collecting cases permitting consideration of a document that is integral to plaintiff's pleadings, even when plaintiff fails to attach it to the complaint). Indeed, the complaint is "replete with references to the contract[] and requests judicial interpretation of [its] terms." Chambers v. Time Warner, Inc., 282 F.3d 147, 153-54 & n.4 (2d Cir. 2002) (explaining that the court may consider a document outside the pleadings "where the complaint 'relies heavily upon its terms and effect,' which renders the document 'integral' to the complaint."); see, e.g., Compl. ¶¶ 19, 32, 62, 77, 88, 89, 106-07, 110, 179-82, 185-88, 198, 202. Therefore, these General Conditions will be considered in ruling on this motion.*fn1

As this motion is being treated as a motion to dismiss under Rule 12(b)(6), the critical inquiry with respect to each of plaintiffs' claims is whether the complaint contains "enough facts to state a claim to relief that is plausible on its face." Bell Atl. v. Twombly, 550 U.S. 544, 570 (2007). In determining whether this standard has been met, the complaint is to be construed liberally, with "all factual allegations in the complaint [accepted] as true, and . . . all reasonable inferences [drawn] in plaintiff's favor." Hayden v. Paterson, 594 F.3d 150, 160 (2d Cir. 2010) (internal marks omitted).

(2) Claims Under Section 1983

All of plaintiffs' federal law claims are brought pursuant to 42 U.S.C. § 1983, which provides:

Every person who, under color of any statute, ordinance, regulation, custom, or usage, of any State . . . subjects, or causes to be subjected, any citizen of the United States or other person within the jurisdiction thereof to the deprivation of any rights, privileges, or immunities secured by the Constitution and laws, shall be liable to the party ...


Buy This Entire Record For $7.95

Download the entire decision to receive the complete text, official citation,
docket number, dissents and concurrences, and footnotes for this case.

Learn more about what you receive with purchase of this case.