Pacheco v. Kew Garden Hills Apartment Owners

NEW YORK SUPREME COURT, APPELLATE DIVISION, FIRST DEPARTMENT


May 20, 2010

JESUS PACHECO, PLAINTIFF,
v.
KEW GARDEN HILLS APARTMENT OWNERS, INC., DEFENDANT-RESPONDENT, H.A.R. CONSTRUCTION, INC., DEFENDANT, HEADSON CONSTRUCTION, INC., DEFENDANT-APPELLANT.

Order, Supreme Court, Bronx County (Norma Ruiz, J.), entered April 16, 2009, which, to the extent appealed from, denied defendant Headson Construction, Inc.'s motion for summary judgment dismissing plaintiff's Labor Law § 240(1) and § 241(6) claims as against it, unanimously affirmed, without costs.

Published by New York State Law Reporting Bureau pursuant to Judiciary Law § 431.

This opinion is uncorrected and subject to revision before publication in the Official Reports.

Gonzalez, P.J., Friedman, DeGrasse, Manzanet-Daniels, RomÁn, JJ.

21309/03

Contrary to Headson's argument, the evidence does not demonstrate conclusively that plaintiff's injuries did not arise out of work delegated to Headson by the general contractor, thereby eliminating Headson's liability under Labor Law § 240(1) and § 241(6) as the general contractor's agent (see Russin v Louis N. Picciano & Son, 54 NY2d 311, 317-318 [1981]; see also Carter v Vollmer Assoc., 196 AD2d 754 [1993]; Davis v Lenox School, 151 AD2d 230 [1989]). Therefore, Headson's argument that it did not direct, control or supervise the work of the general contractor's employees is unavailing because its contract authorized it to supervise and control the work delegated to it (see Ross v Curtis-Palmer Hydro-Elec. Co., 81 NY2d 494, 500 [1993]; Weber v Baccarat, Inc., 70 AD3d 487, 488 [2010]), and its argument that Industrial Code (12 NYCRR) § 23-5.1(h) is inapplicable because Headson was not responsible for the scaffold from which plaintiff fell is unavailing because its contract required it to furnish the scaffolding necessary to the performance of its work.

THIS CONSTITUTES THE DECISION AND ORDER OF THE SUPREME COURT, APPELLATE DIVISION, FIRST DEPARTMENT.

20100520

© 1992-2010 VersusLaw Inc.



Buy This Entire Record For $7.95

Official citation and/or docket number and footnotes (if any) for this case available with purchase.

Learn more about what you receive with purchase of this case.