Anthony J. Gordon, Plaintiff-Appellant-Respondent v. Board of Managers of the East 12th Street Condominium

New York Supreme and/or Appellate Courts Appellate Division, First Department


January 17, 2013

ANTHONY J. GORDON, PLAINTIFF-APPELLANT-RESPONDENT,
v.
BOARD OF MANAGERS OF THE EAST 12TH STREET CONDOMINIUM, ET AL.,
DEFENDANTS-RESPONDENTS-APPELLANTS, 16-20 REALTY ASSOCIATES L.P., ET AL., DEFENDANTS.

Gordon v Board of Mgrs. of the E. 12th St. Condominium

Decided on January 17, 2013

Published by New York State Law Reporting Bureau pursuant to Judiciary Law § 431.

This opinion is uncorrected and subject to revision before publication in the Official Reports.

Mazzarelli, J.P., Andrias, DeGrasse, Richter, Clark, JJ.

Order, Supreme Court, New York County (Salliann Scarpulla, J.), entered April 18, 2012, which, inter alia, denied plaintiff's cross motion for partial summary judgment and upon a search of the record granted summary judgment dismissing his first and second causes of action, denied as moot his motion to quash non-party subpoenas, denied defendant Board of Manager's and Key Real estate's motion for summary judgment on their counterclaim and denied defendant Sweet Construction's motion for summary judgment dismissing plaintiff's claim against it as untimely, unanimously affirmed, without costs.

In this action by plaintiff condominium owner to recover damages for repairs made to a concrete slab in the ceiling above his condominium unit after a portion of the slab collapsed while he was having alteration work performed to the unit, the motion court properly determined that plaintiff is liable for the cost of the repairs made to the entire slab because he voluntarily assumed the obligation to make the repairs, seeking approval for the work repairing the entire structural slab almost immediately after part of it collapsed and waiting a lengthy period of time before requesting reimbursement.

The November 2009 release did not apply to work that was not done pursuant to the alteration agreement or to continuing obligations, and thus did not bar the Board and Key's counterclaim for attorneys' fees incurred after the settlement date (see Morales v Solomon Mgt. Co., LLC, 38 AD3d 381, 382 [1st Dept 2007]); however, the attorneys' fees sought were not for "property damage" under the authorizing provision of the alteration agreement (see Hooper Assoc. v AGS Computers, 74 NY2d 487, 491-492 [1989]).

The motion court correctly found that plaintiff's claim against defendant contractor Sweet was timely. The claim accrued on the date of the injury, not on the date of completion of the construction because it is a tort claim (see IDF Constr. Corp. v Corddry Carpenter Dietz & Zack, 253 AD2d 89, 92 [1st Dept 1999]).

We have considered the parties' remaining contentions and find them unavailing.

THIS CONSTITUTES THE DECISION AND ORDER OF THE SUPREME COURT, APPELLATE DIVISION, FIRST DEPARTMENT.

ENTERED: JANUARY 17, 2013

CLERK

20130117

© 1992-2013 VersusLaw Inc.



Buy This Entire Record For $7.95

Official citation and/or docket number and footnotes (if any) for this case available with purchase.

Learn more about what you receive with purchase of this case.